Industrial Factories

Overview

 

A logistic centre that includes: a production floor with an area of 2,000 square metres, warehouses spanning an area of 2,000 square metres, built in an accurate technology, and an office building that spans 2,000 square metres and includes an industrial kitchen.

The work carried out by Ardan Projects included: accompanying the plant from the initial performance stages, required preparations for future systems, erection of a main energy station that operate in low voltage, main electricity rooms that operates in low voltage, a lighting array and busboards for distribution of feedings to a production machine.

More Information

Erection of a new, high voltage plant, for establishing a factory for manufacturing security systems. The plant has 2 high voltage transformers, electricity boards,

low voltage systems + generator, fire detection and air conditioning system, including development lighting.

Photo Gallery